  • Meeting 1

    -Initial Ideas Brainstorm
    -3 songs found
  • Meeting 2

    -Gave feedback and chose videos
  • Meeting 3

    -Class Pitch with feedback received
    -Ideas filtered and processed
    -Decision on 'Stay' song.
  • Meeting 4

    -Lyric Timeline roughly created by marking all of my ideas next to a place in the song
  • Meeting 5

    -Lyrics Timeline Completed
  • Meeting 6

    -Stealomatic ideas started
  • Meeting 7

    -Editing began on stealomatic
  • Meeting 8

    -Stealomatic Finished
  • Meeting 9

    -Storyboard initial ideas started taking inspiration from my stealomatic creation
  • Meeting 10

    -Storyboard for music video expanded and an ordered sequence began to show.
  • Meeting 11

    -Ideas discussed today for potential artists to use for the music video
  • Meeting 12

    -Lip Sync task of potential artist completed. Feedback was received today as well and the artist was confirmed for the shoot.
  • Meeting 13

    -Photos taken of the artist for the album art and website.
  • Meeting 14

    -Photos from the shoot were taken, screened, and edited in 3 different styles. A vibrant colourful profile, more of a muted tone and black and white for each image. So i could compare the styles and see which would best suit the artist and her image.
  • Meeting 15

    -Digipak research started collating ideas from artist of the same genre
  • Meeting 16

    -Digipak research presented and uploaded to blog
  • Meeting 17

    Student video marking and giving grade was completed in todays lesson
  • Meeting 18

    -Website research started and collated onto a powerpoint
    -Uploaded to blog
  • Meeting 19

    -Storyboard started
  • Meeting 20

    -Ideas for storyboard continued
  • Meeting 21

    -Storyboard voiceover recorded and started the edit for the upload
  • Meeting 22

    -Shooting Schedule was started and derived from the storyboard today
  • Meeting 23

    -First Shoot day today with Toby. Filming went well and we stuck to the shooting schedule and reviewed the footage and posted a 'Day 1' review on blogger.
  • Meeting 24

    Halfway evaluation editing started with the footage and the drafts of the website and the first cover of the digipak.
  • Meeting 25

    -Halfway Evaluation editing finished and exported.
    -Uploaded to blog
  • Meeting 26

    -Halfway evaluation was received, evaluated and upload to blogger
  • Meeting 27

    -Filming day 2 with Lucy, after completion of the second shooting schedule.
    -Evaluation of the shoot day uploaded to the blog
  • Meeting 28

    -Editing started on first draft of the music video
  • Meeting 29

    Editing continued today
  • Meeting 30

    -First draft of music video exported and uploaded
  • Meeting 31

    -Draft 1 construction feedback received, along with draft 1 of website and digipak feedback.
  • Meeting 32

    -Feedback from all media evaluation and posted on the blog with improvements listed
  • Meeting 33

    -Tour poster started, and finished
  • Meeting 34

    Editing on music video continued
  • Meeting 35

    Digipak completed
  • Meeting 36

    -Website final draft completed
    -Still with final video to be uploaded to fill the place holder
  • Meeting 37

    -Editing Continued
  • Meeting 38

    -Construction Draft 2 feedback revived and evaluation from teachers and ex student
  • Meeting 39

    -Final Construction Completed